Trying to Get Beyond 80% Done




The frustrating thing about the remodel now is that lots of things are almost finished; but not many things are actually finished.

The kitchen floor is complete, but the wine fridges can't go in because the walls haven't been painted. The kitchen cabinets still need adjustment. The office is ready to have the floor installed and the walls painted. The light fittings also need to go in. The exterior lights are here, but awaiting installation. The laundry is awaiting cabinet pulls and painting. (We're also waiting for the correct top half of the dutch door to come.) The interior doors are in and painted, but still need the correct hardware (handles, hinges etc). The family room floor is complete and the window bench is in, but the TV cabinet is having to be remade (see earlier post about how it was made up in the wrong material). The guest bathroom tile is half done. The window frames have all been painted, but the glass needs cleaning up.

The guys from Jim's Bunch have been installing the closet doors in our bedroom since yesterday. California Closets will be coming on Friday to install the innards.

I could go on. All this is not to say that work is slowing down, or that the guys aren't working hard, because it isn't and they are. It's just that it would be nice to see something actually 100% complete because every room in the house is currently impacted by the remodel.

Thursday, February 25, 2010

Photos of the New Kitchen









Cabinets - clear stained alder
Countertop - Caesarstone in "oyster"
Floor - porcelain tile with stone mosaic accent
Appliances - pre-existing

All we have to do now is choose the color of the plates for the electrical outlets and light switches. Do we want biscuit, eggshell, pale almond, or simply white?

Who knew there were so many vital decisions to be made in a remodel?

Monday, February 1, 2010

Activity Before the Rain

It poured on Friday night. The weekend was dry and fine, but the sky is darkening now. The Cardboard Box is surrounded on all sides by people working away, trying to get things finished before rain starts up again. We are forecast to have rain tomorrow and all through the rest of the week, peaking on Friday with another monsoon.

In the back yard, the hardscaping guys with the CAT have been digging trenches, back-filling and compacting all morning. They've just finally ripped out the remnants of the lawn in preparation for puttin gthe disipator into the ground. At this moment the digger is getting tangled up in the gopher-resisting net that our gardener installed under the lawn a couple of years ago. The guys look a bit surprised.

Out front, the men from Jim's Bunch are busily wrapping a 15 lb felt moisture barrier around the exterior of the additions. Site Supervisor II explains that this is the final frontier for penetrating damp coming in from the outside. The additions will be pleasingly black and shiney when they have finished.

The roofing people were out this morning too, replacing all our remaining old gutters with new galvanised steel ones. None of them are painted though. I expect that painting them will turn out to require yet another "change order" and an additional expense. Presumably the activity can be picked up when the house exterior is painted. The forthcoming rain will be a good test of their weather-worthiness.

In the kitchen, not much happening today. The dry wallers are there again. That may be putting a stop to the cabinet installation. I shall go and have a nose later on.

Noisy drilling on the outside of the house outside the kids' bathroom resulting in the removal of a strip of stucco and the peeling back of the chicken wire underneath. Hmm. Can't quite see what that is for, though Azmir worked away at it with a will for over an hour.

Over the weekend we chose paint colors for the kitchen and the office/laundry addition. Honeywheat for the office and Golden Labrador (can you believe it) for the kitchen and laundry. Swiss coffee for the ceilings (that's off-white to you). We also went back to Artistic Tile to make yet another selection of tile for our kitchen floor. We went for something that is similar to the last one, but a little colder in tone. The main thing was that it wouldn't take weeks to arrive, as the tiler reckons he'll be ready to start at the end of this week.

Thursday, December 17, 2009

The Agony of Choice


Just look at the lovely collection of items our architect left today. Hubby will be so thrilled to see the different things he needs to help choose... fabric... grommets... paint... Caesarstone...