Showing posts with label electrics. Show all posts
Showing posts with label electrics. Show all posts

Tuesday, September 28, 2010

Maybe a third of one percent away from completion...?

Gosh, I see it has been two months since I last posted on this blog, which is a sign that the house really is so very, very close to completion that there isn't much to say.

We went away on our UK vacation in August, and returned to find the house apparently finished. All the outstanding items on our punch list had been taken care of, with the exception of the exterior lights snafu at the front of the house. We can only have the motion sensor light on if the two garage lights remain switched on; so we end up with the garage lights on all night in order to ensure that the motion sensor light - essentially a fancy security light - would come on if someone approached the front door. The electricians who worked on the house deny having tampered with this electrical circuit, and so fixing this is seemingly outside the scope of the job. (The fact that the lights never had that problem before also seems to be immaterial.)

So we have been living with the house for a month, picking up little things here and there that need fixing. Nothing too major, I hope. The motion sensor light in the back yard isn't working at all. The motion sensor light outside the laundry room door only comes on if you approach it whilst waving your arms in the air. Then there is a bunch of small carpentry items: creaking or rubbing doors, sticking drawer, misaligned bolt, that kind of thing. I hope that Site Supervisor II will be able to tackle most of them pretty quickly, though I wonder whether the electricians will deign to visit us for the electrical fixes.

We had a "duh" moment today. The light in the pool stopped working and we couldn't understand why, as it had been working just fine. Anyway, in an email, SS2 mentioned "the exterior GFI", so I had an "ah ha" moment...took Hubby out into the back yard with a flashlight...found an outlet in the exterior wall and got him to inspect it. Sure enough it had a reset button, which we duly reset and - ta da! - like magic, the pool light came back on. What a team we all are.

Monday, July 12, 2010

Can't Get Enough of That Outdoor Living Thang

I've been spending money again. Today I ordered another extending patio table - this one extends to 130", a full 20" longer than the last one - with six chairs, a 10' by 13' rectangle patio umbrella (in taupe Sunbrella fabric), and an umbrella stand capable of stabilizing 70lbs of weight. As the umbrella is custom made, it won't be ready for about four weeks (i.e. the end of the summer), but the table and chairs will be here next Tuesday. This will give us dining capacity for 22, which is about what we need.

I've also sent my three old teak chairs - purchased about 13 years ago in England - to the patio furniture vendor to be refinished to their original brown color.

Meanwhile, back at the outdoor kitchen, the appliance guy was here again today to tweak the warming drawer, which is now straight in its space.

Inside the house, SS2 was here this morning with Dave the Bath Vendor, who started refinishing the tub in the guest bathroom. It stinks.

Remaining items:

The House:
- two exterior lights are not working.
- screen doors will be coming in about 10 days
- one sliding screen door is loose on its track

The Garden:
- still some plants on site needing to go in
- waiting for some plants to arrive, most notably two espaliered mandarin orange trees for the fence
- grass to be laid in the back
- mulch to be added everywhere
- landscape lighting to be installed (waiting for lights to come)
- the pool cover is still not closing properly every time (small gap on one side)
- pool light is not working, and different subcontractors are currently blaming each other
- mastick around the pool
- cleaning and re-sealing of the stone patio(to combat the redwood staining)
- doors under the outdoor kitchen sink need adjusting (one has sagged)
- fence repair where a couple of planks have fallen down
- creation of gate next to the office, for the "dog run" area
- a stone has fallen out of the hardscape and needs to be glued back in

Thursday, May 20, 2010

A Final Big Push

Site Supervisor II let us know that he was on a training course earlier in the week - becoming certified in lead paint abatement, I bet that was exciting - which is why we hadn't heard from him. Well, we've sure been hearing from him today! SS2 has orchestrated a great influx of subcontractors in an effort to polish off all the remaining work.

First of all, the painters have arrived with avengance. They are currently painting the living room, dining room, and the hallway, all at the same time. I opted to have these areas painted the same color for speed and consistency, a kind of inoffensive beigey color. "Do not move any of the furniture!" orders the head honcho. So it looks like we'll be huddled in the kitchen today (but then again, we all seem to huddle in the office most of the time, so what's new?).

The electricians have been back. They repaired our phone line (which they broke on Tuesday). They are also wanting to charge us a lot more money to get the kitchen skylights working, including $800 for new transformers. SS2 has gone slightly mad at this cheekiness and is planning to bring in a new electrical firm to finish the work. The current electrician apparently had a tantrum and stormed off in his car. Gosh, drama.

In the family room, the cabinet makers have been inspecting the results of their own handiwork: Splintered veneer. I think I mentioned before that the lower cabinets on the TV unit had been delivered without any holes drilled for the adjustable shelves on one side of each cabinet. (Some genius at work there.) After much discussion, and attempts to avoid having to do anything about it, the cabinet people came back on Monday and drilled some holes. Which would have been fine except that they decided to drill from the existing hole on one side of the wood, through the wood and out the other side....with the result that the veneer was pushed out of place and splintered. (Perhaps the same genius at work?) I'm no carpenter, but even I could have told them that was what was going to happen if you push at veneer from the wrong side!

Anyway, they then said that they'd need to order special something or other to get this fixed and it would take several weeks...blah...blah. SS2 went balistic and told them that they need to fix it today. I only got his report of his language to them, and even that was fairly fruity. So we shall see. (I have every intention of naming and shaming the cabinet company in this blog at the end of the project - it will be well deserved.)

The tiler is here too, installing the glass shelves in the guest bathroom shower niche. When the painters have finished the main rooms, they'll be moving on to the touch ups in the other rooms: guest bathroom, family room, Deep Thought's room.

Could it be, are we really, no surely not.... Not almost done for real?

Tuesday, May 18, 2010

Slow progress...but will it never end?


Welcome to week 29 of our remodel.

I know things have been quiet in the Cardboard Box's blog recently. Well, there's not been a whole lot to report. First of all, we've had rain again. Bah. Second, we've been waiting, and waiting, and waiting...for subcontractors...for supplies...for an act of God maybe.

Site Supervisor II had a bit of a triumph last week on the kitchen skylights. He finally found someone who actually knew something about Velux windows. The diagnosis was that we need insect screens which will keep a magic button depressed, thus enabling the windows to open. They are now on order and, in the meantime, SS2 has put a stick pressing one of the magic buttons, and we now have an openable window. Yay! He's installed the new blinds too. We're waiting on a new transformer and new keypad, and hopefully that will result in the skylights being fixed.

The electricians came back yesterday to install the exterior lights. (We still have a couple on back order.) They also installed a couple of new telephone plates inside - with the result, it seems, that our phone is now out of order.

It would be nice if we could finally get the interior of the house fully complete. We have new furniture on the way for the family room, and we particularly don't want painting to be done after it arrives. We've not seen a sniff of the painters and the majority of the outstanding work is now for them.

Alas, SS2 has gone off to start supervising another job which is not so close to completion. I fear this will result in a long slow tail of our unfinished items being polished off.


On the landscaping, the inclement weather has not put the hardscapers off. They can't grout when it's wet, but they have finished laying all the ashlar paving. They've done an amazing job of laying out the crazy paving, and are waiting for the weather to improve before mortaring it. In the meantime, they've moved on to the stone cladding on the back wall, under the redwood trees, and the walls of the outdoor kitchen. I'll take photos tomorrow when it's not pouring with rain.

Just paid a bill for almost $8,000 for the granite countertop for the outdoor kitchen.

Finally, a prize to anyone who can explain why we have this little witch's hat on the roof?

Saturday, May 8, 2010

From Crazy Paving to a Good Night's Sleep

On Friday, SS2 was hardly here at all, and it was peaceful inside the house. The one piece of bad news that he did bring was that the electricians had thrown their hands in the air in despair and declared that the skylights in the kitchen could not be repaired; and that the construction team would now need to deal direct with the customer service people at Velux. SS2 views this prospect with a sinking feeling, having had poor experiences with other manufacturers' customer "service" departments.

Progress on the hardscaping and other elements of the exterior work has picked up the pace.

Outside the house, the hardscapers completed the grouting of the stonework in the front yard, and very smart it looks too. They immediately moved on to laying the stone in the side yard and where the pergola will be. Not content with the jigsaw that is the ashlar pattern, we have asked for the pergola area and side path to be constructed of irregular, crazy paving style stones. Amazingly, the main stone guy is doing a fabulous job of fitting it all together. He really is a highly skilled worker.

The stucco subcontractor completed the finish coat on the house and also on the front wall. It's looking quite striking out there, even imposing. The stucco is a creamy white color. I must say that Hubby and I are finding that quite appealing, and wondering if we'd like to leave it light rather than having it painted Brewster Gray like the house.

The technician from Pool Covers Inc arrived and installed a bright blue pool cover. This is, alas, the wrong color. It should be grey. I only noticed him out there at the point when he was finishing the work. To say he was a bit downcast when I told him would be an understatement. Well, this will stay on the pool for a week or so, and then be replaced by the correct color, so no harm done.

The solar heating for the pool seems to be working fine.


This morning I got rid of our filing cabinet through Freecycle. We also had our new bed delivered - moved the old bed into the new guest room and enlisted friends to put it together - and also had the piano moved back into the family room...just in time for Mothers' Day tomorrow. No 6:30am wake up call from Little Starlet.


Hubby finally unpacked his new espresso maker. It may take us a while to really understand out how to use it....

Thursday, May 6, 2010

The Creation of Beautiful Smoothness

The theme of the day is smoothness.


Inside the house, SS2 has been working on patching the walls in the living room, following the moving of some of our light switches.


Outside the house, the workers from the hardscaping company are grouting the stone in the front yard.


The stucco subcontractors are applying the final coat to the exterior of the house, and are doing a wonderful job at making everything look even. They are also putting the brown coat on the garden wall out front.


Finally, the pool is almost full of water - and glassy smooth (despite the gunk floating in it!).

Wednesday, May 5, 2010

Wet and Wonderfully Smooth

It's been a busy day around the Cardboard Box today. Site Supervisor II is anxious to be done with the inside.

The electricians finally showed up fully equipped with their tools. They replaced and fixed most of the small things on the list. The sky lights in the kitchen are still not working, but they diagnosed that the transformers are faulty/defunct. They are going to try to source new ones for tomorrow and come back to install them. They did move the three light switches in the living room that were floating free on the walls, far from the wooden trim; and also installed a new outlet in the kitchen over the wine fridges. Hubby will be pleased as this means he can now set up his new coffee maker.

SS2 has installed the trim strip at our master bedroom exterior door and has repaired the sliding door in the guest bedroom which stopped locking yesterday.

Outside, the stone work has continued. The front is almost done. The fence is complete, all we need is the new gate by the guest bedroom, which has to wait for the wall to be stuccoed. Speaking of which, the wall has been prepped for stucco, with a wire frame added to all the edges.





The big news of the day is that the pool has been plastered and we are currently filling it up with water. We have to leave it filling overnight. If the water is turned off, then a water line will form on the new plaster. (We chose French Grey "Wet Edge" plaster, which is supposedly the smoothest on the market.)

Monday, April 19, 2010

C-Day Arrives...and Leaves

Today was supposed to be punch list day, which we might also term Completion Day. Over the course of last week, this became reframed as "punch list for the interior" day. In the event, it was not completion day at all.

Don't get me wrong: The project is very close to being finished (at least inside the house), but every room has something in it that needs completing, tweaking, fixing, touching up, etc. On the instructions of Site Supervisor II, I went round the house - though not the family room/ bathroom/ bedroom end - this morning with a pad of paper and some painters' tape, obsessively opening drawers, looking for scuff marks, and such like; and I sent him a list of 29 items requiring attention. Since sending it, I've spotted two more, but 29 seems like enough to be getting on with for now.

The list includes things like electrical receptacles unfinished, the phantom screens on the office windows being sticky, some minor dry wall damage in the dining room, scratches on the top of the dresser in the master bedroom.... By themselves, nothing major, but adding up to enough work to keep them busy for a few more days at least.

The only rooms that are finally complete are the master bathroom and Deep Thought's room, which were having only minimal work done to them anyway. The guest bedroom looks done, but then you discover that the lights inside the closet have not been wired in. The family room looks done, but then you open the TV cabinet and discover that the shelves where the DVD player and other kit should sit are not straight as the holes for the pegs to hold them have not been drilled at the same level (I kid you not). The office looks done, but the desk grommets need to be secured in place and the screens need correcting. You get the idea.

To say that SS2 is frustrated by the lack of finishing would be an understatement, I think. The cabinet makers reached the top of his hit list again last week, having made medicine cabinets for the guest bathroom that were too large to allow the light fittings to go between them (despite the light fittings having been in our garage for three months). Hubby is also getting pretty fed up with the endless fiddling about that is required at this stage. I am trying to be stoic about it as I have to live with it - and answer multiple questions every hour on all manner of subjects, from handle placement to likely mode of using the windows.

The two big steps forward of the day seem have been having door handles (well, actually finger cups) added to the office doors, which now look rather stylish; and the finalization of the cable man's work on the telephone, ethernet and cable installation. We now have a "smart panel" on the wall in the TV cabinet that should eliminate any need for ugly grommets and wires on show.

Thursday, April 8, 2010

Where did the week go?

Here we are at Thursday! I've been so busy this week it's been impossible to get to the blog. Plus our internet connection has been having some screwiness - we think Comcast, rather than the remodel - which has been frustrating. But here I am now.

Landscaping - We accepted a bid from a landscaping firm, and they'll be here on Saturday to start clearing up the back yard and prepping the soil. The stonework guy returned to work and has been laying the patio out back. It looks great.

Remodel - Site Supervisor II is compiling a hit list of subcontractors. High on his list are the cabinet people, who have delivered the TV cabinet wrongly made for the second time. (As I write, the painters are shouting angrily at each other in Serbo-Croat in the family room...I think there may have been an "oops" moment. I try not to notice.) The electrician has gone AWOL, but it sounds like if we get to a critical mass of things for him to do then he will come back. The hinges for the interior doors were delivered - in the wrong size. I've filled our closet with clothes twice this week...and then had to take them all out again.

Anyway, it's been a bit like that all week. I think SS2 may explode with frustration soon. (The head painter is now scolding his workmen in English. I can't see them, but I can sense them hanging their heads in shame.)

Our microwave oven has been installed by SS2 (who has started simply doing the work himself instead of delegating it), and we also got the new dryer. SS2 and the plumber installed the washer/drier units, and managed to get them closer to the wall than the original installers.

Jim and SS2 claim that we'll still be finished on April 12. The Architect is skeptical. Well, I guess we'll see.

In other news, our large purple window seat cushion was just delivered. I do hope it fits.

Sunday, April 4, 2010

Wet Weekend Round Up

So little seemed to happen last week that I gave up writing the daily blog. So here's a brief summary of action:

- wood floors went into the bedroom, office, and the base of Little Starlet's closet, and each received their sanding and first two coats of varnishy stuff;
- the gimble mounted lights went into the bedroom and office ceilings;
- the snap-on outlet plates were installed in the kitchen (mostly);
- the baseboard and crown molding were painted in the master bedroom;
- the tile was almost finished in the guest bathroom, except for a small area around the toilet sewer pipe;
- the tub deck in the guest bathroom had the corner rounded to eliminate potentially injurious point;
- some of the cabinets in the kitchen were adjusted (again);
- the shelf inserts inside the main food pantry were installed - but they have to be removed because now the rolling shelves have no way to come out.
- the door bell was repaired, and now plays the first couple of bars of the 1812 overture (not sure this is a big improvement on the last tune).
- wood siding installation began on the exterior of the bedroom/bathroom
- the "scratch" coat for the stucco was installed on the office/laundry and the rear main wall.

That may sound like a lot, but is actually not a great deal. Most days we only had one or two guys here, which is a big difference. There was no action in the landscaping at all, as our stone layer was off with family issues.

In other news, I had a bit of taxpayer triumph. A couple of months ago, Site Supervisor II spoke with the City about repairing our sidewalk and road. The City told him that it would be ten years before they were back on our street, and that we were essentially out of luck. Last week I took matters into my own hands - inspired by new puddled formed by new rain - and contacted the Public Works Department. Long story short, they came to inspect and agreed to add our section to their repair schedule for 2010. In fact they said there were 20 places on our street that needed repair, so they'd be repairing the whole block! Hubby says, maybe they checked the computer to see how much property tax we pay....

Friday, March 5, 2010

Traffic Calming

Yesterday we had 15 trucks outside out house, including an enormous concrete mixer. Today was much quieter, just five vehicles.

The landscaping crew continued their work on setting up the forms for the front yard concrete (due to be poured on Tuesday, weather permitting). I have to forgive them their last trench, upon which I poured such scorn, as it turned out to be the base for the courtyard wall.

The guys from Jim's Bunch continued working away inside the house. They ripped out the inside of the closet in our bedroom. They have installed the dresser in our bedroom, and also finished off the wine fridge area in the kitchen. Various bumps and hammers from other parts of the house, tasks unspecified. Everything seemed quite calm today.

Site Supervisor II declares that the job will be finished in six weeks.

Photos here:
i) The old hot tub box on the side of the house, where our predecessors kept the water chemicals and stuff. We're having it taken off - retaining the potentially useful electrical outlet, because you can never have too many - and the wall made good. This photo gives a little peek into the way the house is built, with stucco, paper, chicken wire and lumber.
ii) The dresser in the master bedroom in process. This will be painted.
iii) The back yard as viewed from the redwood trees. The concrete was dry enough for me to venture out this afternoon.
iv) The fancy metal flashing at the weep screed which now extends all around our house's perimeter. Apparently this is state of the art and will block any pesky termites from finding their way in. (The little blighters had eaten quite a lot of our door steps and similar, it turns out.)
v) The wine fridge area in the kitchen almost done. I live in hope that the fridges will be moved into the kitchen and out of our dining room early next week.





Monday, March 1, 2010

Have you been paying attention? Finish this sentence: "Another Day..."

It is Monday. Welcome to week 21 of the remodel. Guess what joyful occurrence has gladdened the hearts of the Cardboard Box dwellers today? Yes, a new hole in the front yard. In fact, to be specific, two holes. The first hole is involved in a sewer relocation connected to the "outdoor kitchen" we are building in the back yard. The second hole is to accommodate a pipe that was the subject of installation in a previous hole. This landscaping crew is worthy of employment with BT or British Gas or one of those wretched utility companies. Site Supervisor II says he tried not to notice what they were doing, it was too painful to watch.

Inside the Cardboard Box, the dishwasher finally came back to life today. Unfortunately it leaked into the cabinet under the sink. Turned out to be something to do with gravity and one of the pipes having a dip in it. Anyway, SS2 called the plumber in to fix it and told him very sternly that the whole kitchen remodel was predicated on eliminating the leaking faucet and water damaged sink cabinet, so it had better get put right. SS2 is a pretty mild mannered guy, so it's easy to see when he's not tremendously impressed. While he was here, the plumber also swapped the Insinkerator (garbage disposal) around from the big sink to the small sink, and installed the second Insinkerator in the vegetable sink. Houston, we now have total sink capability.

We've spotted various little fixes that are needed around the kitchen, but we've decided not to moan on about them just now. We'd rather the guys get on with some of the remaining big stuff than spend their time fiddling with the little stuff. That can wait for the punch list at the end, if necessary.

Our whole house fan was working over the weekend, but isn't now. We discovered that the attic fans had been left switched on, so we turned them off at the subpanel. SS2 said that the thermostatic controls for the attic fans would be installed today. Quite what actually happened I'm not sure: The attic fans are still permanently on, while the whole house fan is no longer working. It seems like that with all our electrical work: One thing gets fixed and another stops working. The electicians claim that we have funky wiring (and I can believe that) but even so, surely this isn't absolutely necessary.

The carpenters continued working on the windows today and seem to be close to finishing.



In other big news, the pocket doors for the kitchen/study wall have arrived. Yay! A couple of the guys from Jim's Bunch started to install the pockets this afternoon. This is arguably the last big piece of actual construction needing to be done. When the pocket doors are in, they'll be able to finish the drywall in the kitchen, the tile floor, install the last cabinet, and take the blessed wine fridges out of the dining room at last. All good stuff.

Now, to return to yesterday's important question about the light switch in the living room, here is a photo of it. Would you have it moved or not?

Sunday, February 28, 2010

Might as well madness......?

It seems that "might as well" madness is setting in around the Cardboard Box. These are well known to be highly dangerous words in a remodel situation. The phenomenon involves looking around your house, noticing things that aren't perfect, and commenting to each other "While we're doing [XYZ], we might as well [put that right]."

The focus of our MAW-ness today concerns the light switch on the living room wall. Now the old thermostat has been removed, it is floating in the middle of the wall. It is also crooked. Will we succumb to paying for the electrician to move it 18 inches to the left, the drywaller to patch the wall, and the painter to repaint?

Watch this space.

Thursday, February 25, 2010

Photos of the New Kitchen









Cabinets - clear stained alder
Countertop - Caesarstone in "oyster"
Floor - porcelain tile with stone mosaic accent
Appliances - pre-existing

All we have to do now is choose the color of the plates for the electrical outlets and light switches. Do we want biscuit, eggshell, pale almond, or simply white?

Who knew there were so many vital decisions to be made in a remodel?

Monday, February 8, 2010

Welcome to Week 18

Week 18 of the remodel. The sheetrock guys were here the whole of Saturday putting the walls up in the kitchen, laundry and office. They are here this morning putting the sheet rock up in the bedroom/bathroom/family room. Lots of drilling. Here are a couple of photos of the bedroom with blown-in cellulose insulation on the walls and ceiling, pre-sheetrock; and the laundry post-sheetrock. You can see the new electricity subpanel at the right in the laundry.




Work continues in the kitchen. The countertop guy is here this morning. We've just had "one of those conversations" about the location of the main sink, where I'm being asked to say if I want the sink two inches to the right or the left on the basis of something I can't see. I'm sure it'll be fine....

Here is a photo of the kitchen as it stood on Sunday, and also the office. Kinda looks like a room now, doesn't it?




The electricians are whirring away behind me as I speak. I think they're trying to fix the outlet that has never worked in the dining room. Maybe they'll even get to fixing the outlet boxes in the living room floor today - Deep Thought bruised her foot on one last week, so we're keen to see them put right.

Finally, the landscaping crew is outside in their digger removing the final bit of concrete in the area where the outdoor kitchen will be. What a job, digging holes for a living.

Tuesday, February 2, 2010

Still no rain, lots of activity

The rain in holding off, so we have teams of guys around the house again today. The hardscaping crew are still in the back yard trenching and adding drainage pipes. I had a discussion with the Hardscaping Boss and the Landscape Designer today about adding an additional 200 feet long trench alongside the pool in order to allow the power, water etc to run from the house to Hubby's blessed outdoor kitchen. This trench will have to be dug by hand and will take two men three days to complete. Does that sound expensive to you?

Here's a photo of the dissipator pipe, and also of the man digging a hole for it in the lawn area. (Look for his head and a long stick in his hands at the center of the photo.)


The house wrapping continues and is nearing completion.


The central vacuum man was here scoping out the work and prepping to make an estimate for the vacuum to be extended into the bedroom/bathroom addition. Turns out that the regular pipe for use with the vacuum is so long we don't need to add attachment vents in the office or laundry.

The lights in the dining room and hall that were out over the weekend are back in action. Apparently the outage was caused by a short in the kitchen. We still don't have a doorbell, but that's hardly an issue since no one ventures over the front yard any more.


This is how the kitchen looked at the end of Sunday. The dry-wallers have now completed their work, the walls have been primed, and the cabinet company is busily completing the installation of the cabinets. Site Supervisor II reckons we lost a day with the dry-wallers taking too long.


Finally, the concrete guys are back, pouring additional concrete around the foundation of the bedroom. You remember the not-perpendicular-house problem from a few weeks back? After the additional foundation material has been poured, it will no longer look like our addition experienced an earthquake.

Thursday, January 14, 2010

Powerless

The big excitement of today was having no electricity. The main subpanel and the electricity meter were moved this morning. We had several inspections during the course of the process, with visits too by the utility company. It all went smoothly. Apart from the electricians, no one else was on site today. (No power, no workers.)

We had our regular site meeting today. The big news from that was that (1) the Caesarstone will cost almost $3,000 more than the number we had last week and (2) the windows are due to be delivered on January 25. Until the windows come, there is little more they can do. That is also the day, of course, that the kitchen demolition is due to start. So I guess we'll have a big surge of activity that week. I should enjoy the peace while I can.

Wednesday, January 13, 2010

Pool progress again

The weather did its Californian monsoon thing this morning. One moment dry and sunny, the next pouring buckets, another moment sunny again. Result: big puddles all across the back yard.

Not much happening in the house at the moment. The electricians were here again today, moving cables and panels and such like, in preparation for a slew of city inspections tomorrow. I hope none of the inspectors cares about the tree protection fencing, which is leaning at a rakeish angle.

According to Site Supervisor II, the house remodel is now being held up by the windows order. They really can't get on with finishing the walls until the windows are installed, which makes sense. I imagine we'll learn more about the impact on the schedule at tomorrow's site meeting.

The landscaping is going along though. The Jolly Demo Man finished clearing all of the rubble away, front and back, and the BobCats have gone again. So we are ready for hardscaping action, pending completion of the necessary elements of the pool. In the pool, two men have been working away today installing the waterline tile and it looks just about done. I'm not sure if coping or plastering comes next.

In other news, yesterday I received three invoices from the Arborist. Turns out that his initial estimate did not include the charges for the crane hire, so his bill is twice as much as his estimate. Also it looks like he is trying to charge me twice for removing the same pine stump. I complained to the Landscape Designer about this - as she recommended we use him - and she said she'd call him.

Friday, January 8, 2010

Darkness all around

Oh, and last night all the lights went out.

Tuesday, January 5, 2010

Catch Up Report

Hello, dear readers (that means you, Anthony). I know you will be worried that my lack of writing will be a reflection of lack of progress, but how wrong you are. Even over the holiday period the guys have been working away, and things are going very well (at least to this amateur's eyes).

Landscaping:

The back yard is now a wasteland. All the concrete has now gone, except for a small piec
e around the pool which they have clearly decided to leave and concrete over, as part of the raising of the grading of the backyard. This was an exceptionally noisy and intrusive part of the whole remodel experience, with three BobCats in the yard at one point, one with a jack hammer attachment, the other two with different kinds of scoops; plus numerous guys with hand-held jack hammers and shovels. The planters are gone, the wall under the trees has gone, the lawn has gone. We have a big pile of mess in the area that used to be designated lawn, including all the loungers and chairs that Hubby wouldn't let me dispose of, and the old pool cover.

The pool has had its coping and water line tile removed, there are several holes punched in the bottom, and the light has been taken out. The bottom of the pool is full of shards of stuff. One of the pool's wall steps has been broken.

(Hold on, a man has just appeared in the ha
llway.)

(Just the electrician looking for the sub-panel.)

The wood framing for the concrete pouring around the pool has been erected, and rebars have been inserted around the top of the pool, presumably to hold the new coping. That is supposed to be arriving in the third week of January.



The little lemon tree that the kids bought for Hubby's 40th birthday is still standing bravely in the midst of all this. I tied some "Caution" tape around a couple of bamboo stakes to protect it, and miraculously this seems to have worked. Elsewhere, the drainage plans have been marked out on the ground in orange paint, so we can now see where the barbeque is going to be and also the planting beds near to the house.

House:
Jim says that we have a delay in the windows arriving, and that will slow down the completion of the walls. In the meantime, his guys are working away on the roof. The bedroom/bathroom addition now has roofing felt, and a pile of cedar shingles is waiting to go on. On the office/laundry addition, the shingles are already going on; the roof over the dining room is finished, and the office roof looks like it may be finished today. While we were away at the snow, the new gutters went on. The guys have also started to rough in the plumbing and electrics. Lots of thick yellow wires are strung across the wall framing, and a lovely black pipe indicates where the washing machine will go.

Current discussion is focusing on the kitchen. We have been scheduled to have the kitchen demolition next week, but our architect is now wondering if it can be put off a week, as we'll be away for a few days in February. Personally I suspect that they will over run anyway, so they may as well over run while we're away.