Saturday, March 27, 2010

Weekend Round Up



Good progress on the guest bathroom.

The floor is almost laid. The grout has gone in among the glass tile in the shower. The wainscoating has also gone in. The corner of the Vetrazzo has been smoothed off. Next step: Installation of the medicine cabinets.

Outside the house, the builders have started installing the wood sheathing that goes underneath the wood siding at the front of the house. I was puzzling about why there was no chicken wire, and of course now I realize. You only do chicken wire if you're doing stucco. Wood siding requires a wood base. They've also been adding the exterior framing for the windows and doors.